4.0.0.Milestone3
- Respin staged
- Lucas and Pavol looking.
- https://jira.jboss.org/browse/RF-9417 already created. Nick will review it.
- Nick also will review all unscheduled issues
- Issues found before staged release reviewed and moved to M4
- Release plan
- QE Verification
- Hudson builds look good.
- Lukas and Pavol are working on metamer.
- Release early next week
- QE Should wrap by EOD Thursday.
- QE Verification
4.0.0.Milestone4
- Jira review this week
- Every one should review theirs issues.
- Nick, Ishaikovsky and I will be reviewing future_4X, and creating the appropriate component jira's for the items plans.
- Initial Dates:
- Component Code Freeze Oct 26th
- Code Freeze Nov 2nd
- Release ~Nov 8th-9th
- Jay will set up post mortem meeting for M3