    Meeting Plan:

    • 0min --> 15min : Release plan
    • 15min --> 40min : M4 dev status
    • 40min --> 50min: M4 QE status & req
    • 50min --> 60min : JBoss Tools Integration

    Milestone 4

    • Release Plan
      • Component code freeze Oct 29th
      • Bug fix, QE prep Oct 29th -- Nov 5th
      • Code Freeze Nov 5th
      • Tag/Release to QE Nov 5th-7th
      • QE testing, verification Nov 7th-12th
      • Release Nov 15th-16th
    • Dev Status
      • Components
        • CSV
        • Select/inplaceSelect
        • Tooltip
        • Calendar
        • Push Updates
        • Tree
        • PanelMenu
          • Likely to postpone
        • Fileupload
          • Postponed
      • Bug work this week
        • Review & plans
        • Updating jira
    • QE
      • Component integration status
      • JBDS/JBoss Tools testing
      • Release timing

    JBoss Tools Itegration