Meeting Plan:
- 0min --> 15min : Release plan
- 15min --> 40min : M4 dev status
- 40min --> 50min: M4 QE status & req
- 50min --> 60min : JBoss Tools Integration
Milestone 4
- Release Plan
- Component code freeze Oct 29th
- Bug fix, QE prep Oct 29th -- Nov 5th
- Code Freeze Nov 5th
- Tag/Release to QE Nov 5th-7th
- QE testing, verification Nov 7th-12th
- Release Nov 15th-16th
- Dev Status
- Components
- CSV
- Select/inplaceSelect
- Tooltip
- Calendar
- Push Updates
- Tree
- PanelMenu
- Likely to postpone
- Fileupload
- Postponed
- Bug work this week
- Review & plans
- Updating jira
- Components
- QE
- Component integration status
- JBDS/JBoss Tools testing
- Release timing