1. Re: Help to implement an Approval Business Process
estaub Aug 22, 2007 1:52 PM (in response to jeanguyer)I don't have any experience in this area, but I see very little useful relevant information outside of the user guide and the source code. Maybe somebody with more experience will respond...
I think the one tricky thing is that you need to immediately terminate the process when anyone DENIES. This could be done easily with a custom TaskControllerHandler, I think. The rest seems like straight JPDL.
-Ed Staub -
2. Re: Help to implement an Approval Business Process
kukeltje Aug 22, 2007 5:32 PM (in response to jeanguyer)You could also try to:
- Create a custom decisionnode that creates enough tasks (see the wiki for an example)