Hi All..!
I am new to JBPM.Could u please help in this..!
I created tasks like this Task1-->Task2-->Task3
after completing the Task1 ,the Task2 is assigned to group of users .
Now my problem is when we assign a task to group of users ..it is showing the corresponding task in the group users list.but if one of the users close the task ,the task is closed.
But my requirement is "The Task has to be closed after all the users in that group close that task" .
Is it possible in JBPM?
I am using jbpm-3.1.4 and Jboss4.0.2
I will be thankful if anybody provide the examples for this.
sorry for my english..!
seeking ur help..!
Thanks & Regards,
Sathya,
Developer
yes it it possible with a custom fork where you create as many tasks as there are users in the group. This custom fork is described in the wiki