1. Re: jBPM 4: Identity and Task projects
yuanqixun Jul 22, 2008 3:48 AM (in response to heiko.braun)"heiko.braun@jboss.com" wrote:
Identity and task have become projects on their own. The jpm4 subversion module now contains three distinct projects:
* Identity
* JPDL
* Task
Hi heiko
How to associate the TaskDefinition and Node or ProcessDefinition? In the pvm,there isn't the the TaskDefinition's reference, and when execute a node's behavior(create a task), how does the execution know the node's TaskDefinition? Please give me a idea, thank you. -
2. Re: jBPM 4: Identity and Task projects
camunda Jul 25, 2008 10:01 AM (in response to heiko.braun)Would be also interessting for me. There were already discussions on this forums on making the task component more generic. Does this idea going this way? How does the connection to the process work then?
Thanks
Bernd -
3. Re: jBPM 4: Identity and Task projects
tom.baeyens Jul 28, 2008 4:09 AM (in response to heiko.braun)that is a work in progress. rough lines are in svn project. though i'm not sure what its current state is given the migration and refactorings. it will be brought in a better shape when i'm working on jPDL, which should be next month.