    Timeboxed development schedule

    kconner

      We are now entering a timeboxed release process. Starting from next week we will be adhering to the following schedule

      3rd March - 14th March (2 weeks)
      JIRA issues will be assigned to the 4.3 release of the project. At this stage we will consider requests for new functionality.

      17th March - 25th April (6 weeks)
      Development work continues through this period. We will only consider additional JIRA tasks if they are definitely bug fixes, new functionality will be assigned to the next release

      28th April - 9 May (2 weeks)
      This period covers the final testing of the project, in readiness for the release.

      If there is anything you wish to see in the next version of the project then please let us know *before* March 14th.

      Thanks,
      Kev

        • 1. Re: Timeboxed development schedule
          kconner

          Update:

          We will be moving the end date of the development work and, therefore, the end date of the release back by one week. The main reason for this decision is to include the work which is currently taking place on the FP branch and verify the integration with AS 4.2.2.

          The new dates are:

          17th March - 2nd May (7 weeks)
          Development work continues through this period. We will only consider additional JIRA tasks if they are definitely bug fixes, new functionality will be assigned to the next release

          5th May - 16th May (2 weeks)
          This period covers the final testing of the project, in readiness for the release.

          Apologies for this.

          Kev