1. Re: CTS progress
ovidiu.feodorov Jun 27, 2005 1:20 AM (in response to ovidiu.feodorov)85.61% pass before the alpha release.
-
2. Re: CTS progress
timfox Sep 25, 2005 1:42 PM (in response to ovidiu.feodorov)99.65% - almost there
-
3. Re: CTS progress
ovidiu.feodorov Mar 26, 2006 9:34 PM (in response to ovidiu.feodorov)TCK for beta release is done. All relevant tests pass.
In order to get them passing, I had to set Remoting leasing period to a very large value (see http://jira.jboss.org/jira/browse/JBMESSAGING-276
http://jira.jboss.org/jira/browse/JBMESSAGING-277),
had to temporarily disable support for JMSXDeliveryCount (see http://jira.jboss.org/jira/browse/JBMESSAGING-278), add extra configuration to j2eetck-mods, plus a host of other minor Messaging fixes.