Milestone 2 Release
Nexus server problems solved(just indexing problems but artifacts actually published and available). So binaries ready.
Jay will release docs and upload the distribution to downloads.
QE handles uploads verification
Ilya and Jay handles RFPL-763
Post Mortem scheduled to next team meeting. - Jay preparing agenda at forum
Milestone 3 Release
Some vacations and J1 should be considered!
Sep 21 - code freeze date
Need to review and postpone the tasks if not fit to clean-up the plan
No mock release for M3 - environment was checked in M2 and seems release now working stable
Misc
JBAS integration
- JBAS-8361
- Nick planning to try Mojara 2.0.3
- RF-9282 review by Nick influence the compatibility