4.0.0 Milestone 5
- Component status
- PanelMenu in progress
- Fileupload some issues, but will finish in time
- Toolbar - Ready, waiting for review
- dnd - some issues with client side
- Need to discuss more offline
- Calendar features good
- Drop down menu good
- CSV + Msg - behind a week because of portal work, but still should make component freeze
- Tree features on tract
GAE Showcase hosting
- Load testing last week
- Performed well
- 2 main issues
- Ajax requests failing under load, and making browser restart needed
- Must be resolved prior to announcement
- 404 on some resource requests
- Not huge effect, but should be investigated
- Ajax requests failing under load, and making browser restart needed
- Will reconnect after vacations/holidays ( next week )
- Jira's should be created as needed, and set to "examples" with "GAE" label.
4.0.0.Milestone 4 Post-mortem meeting
- Forum post
- More details in the transcript
- Main points discussed:
- Code Reviews
- Either did not happen, or had very little feedback/results
- Need to make sure we get good peer reviews to help with initial quality
- Git migration
- Nick has been trying it, and liking it
- some issues with windows client
- Any migration will need to wait until at least M5 is out
- Markup delays
- PanelMenu as an example
- Looking into alternate approach
- Req/Dev meeting still going very well
- For some non-trivial components need more impl/design info in wiki
- Code Reviews
- Concerns over postponing jira's
- Priorities have forced some items to shift
- Full reviews need to be done for CR's and that will be the main focus of those phases
- Mojarra version changed post freeze, and examples were not up to date.
- Initial quality of components to QE
- Not really different from QE's point of view
- Should check showcase and dev samples better before freeze
- Engineering suggestion
- QUnit test runner as part of jboss-test suite
- Complete Alex's example template work ( part of CSV )
- Should cover skinning, test components in various containers
- Misc
- Mad dash of jira shifting and resolving at the end of the milestone
- Again - need to make sure that jira is updated regularly so we know how things stand
- CR release schedule discussed ( 1 or 2 week cycles, still in discussion )
- Weekly, or bi-weekly releases of showcase would help dev, qe, etc…
- Can not be public releases though
- Migration is critical and needs to be addressed asap
- Jay and Ilya will meet next week
- Mad dash of jira shifting and resolving at the end of the milestone