    Setting the start date

    caron Newbie

      Hi,

      We are busy implementing jbpm.

      In order to migrate historic data, I have written code to create the tasks, start the task and then end the task. This is working well except I now want to set the start date and end date on the taskInstance to my own dates.

      However, if I look at the code in org.jbpm.taskmgmt.exe.TaskInstance setStart sets the date to null.

       public void setStart(Date date) {
       start = null;
       }
      


      I am using version 3.2.3.

      Does anyone know how I can set the start date?

      Thanks in advance.