1. Re: Can we use JBPM Simulation Programmatically? And Can we do simulation based on current data?
swiderski.maciej Aug 2, 2013 1:24 AM (in response to thomas.setiabudi)1 of 1 people found this helpfulSimulation can be used programmatically as it is designed as layer on top of actual runtime engine. You can find some details about the implementation here.
When it comes to simulating based on actual data it is not supported out of the box but should be quite possible to do so. The only thing is that simulation is usually executed with number of instances where what you described is more like prediction where the process will go next - meaning single instance. So you're probably more interested in path finder component of simulation to show possible paths and then select the most probable one based on the data.
HTH
-
2. Re: Can we use JBPM Simulation Programmatically? And Can we do simulation based on current data?
thomas.setiabudi Aug 13, 2013 12:37 AM (in response to swiderski.maciej)Hi Maciejs,
Thank you, I see the Simulation uses KIE and KJars, does that mean it works only for JBPM 6 ?
Regards,
Thomas Setiabudi
-
3. Re: Can we use JBPM Simulation Programmatically? And Can we do simulation based on current data?
swiderski.maciej Aug 13, 2013 1:01 AM (in response to thomas.setiabudi)Thomas, there is branch that is compatible with 5.4 release and can be found here. The one in master (droolsjbpm-integration) repository is for 6.