1 2 Previous Next 17 Replies Latest reply on May 22, 2008 2:54 AM by timfox Go to original post
      • 15. Re: State of our failing tests
        timfox

        Current status:

        We're almost there :)

        Remaining failing tests are:

        1) Related to missing ping functionality:

        org.jboss.messaging.tests.integration.core.remoting.impl.ClientCrashTest
        org.jboss.messaging.tests.integration.core.remoting.mina.ClientKeepAliveTest
        org.jboss.messaging.tests.integration.core.remoting.mina.ServerKeepAliveTest
        org.jboss.messaging.tests.unit.jms.network.ClientNetworkFailureTest

        2) Related to INVM transport:

        org.jboss.messaging.tests.integration.core.remoting.mina.MinaServiceTest

        3) One remaining ack test

        4) Three old favourite message consumer tests.

        These are actually quite hard to fix, I need to give them some thought.

        So the main thing that remains to be done is finish implementing the pings. Andy - do you have an ETA for that?

        Clebert also is making his timeout configurable and moving the performance tests out of the main test suite

        • 16. Re: State of our failing tests
          ataylor

           

          So the main thing that remains to be done is finish implementing the pings. Andy - do you have an ETA for that?


          that'll be done some time day. that gives me about 36 hours if my calcs are correct!

          • 17. Re: State of our failing tests
            timfox

             

            "ataylor" wrote:

            that'll be done some time day. that gives me about 36 hours if my calcs are correct!


            LOL. Yeah, I find these standard 24 hours days just too constricting, never enough time to get anything done :)

            1 2 Previous Next