1 Reply Latest reply on Nov 1, 2008 2:01 PM by kukeltje

    Possible to allow existing process instance/task to move to

      Hi, assuming i have some process instances running still in version 10.

      Question 1
      And the next moment i deployed a new workflow version 11 with some minor changes without changing the node's transition but the Actionhandlers. I need to move all the existing process instances to version 11.

      How do i move the existing instances to the new version 11 without interrupting the current operations? supposingly this is Live system.

      Question 2
      Supposingly, some of the node and transition changed. Can the existing prcoess instance be move/migrated over transparently? Or some dirty work is required?

      Thanks and regards,