    Task duedate / Reminder duedate

    kukeltje

      In jBPM 3 there was a duedate specifically on the task and one on the reminder. While reviewing the docs for 4, I cannot find the reminder on the task anymore and assume (no sourcecode check done or examples made) it is not there anymore and the duedate on the reminder is used for this. For me they are two different things. The duedate of the task can be later than the first time (duedate?) the reminder is send. For me it is to late to have a reminder send on the day the task itself passes it's duedate.

      Am I right or did I miss something (not so) obvious.