1. Re: Has JBPM 5 the Choreography Task symbol?
salaboy21 Aug 26, 2011 9:34 AM (in response to raquetti)Choreography is not covered yet by jBPM. Right now as far as I know jBPM5 is focused on complete the Process Modeling and Process Execution profile from the spec.
Cheers
-
2. Re: Has JBPM 5 the Choreography Task symbol?
raquetti Aug 26, 2011 9:56 AM (in response to salaboy21)Oh.. Thank you!
Do you know some tool (freeware or opensource) to draw Choreography tasks?
I saw many, but the unique that I could find it, was Eclipse BPMN2.. but many error, terrible that plug-in.
(my complaint about: http://www.eclipse.org/forums/index.php/m/719198/#msg_719198)
-
3. Re: Has JBPM 5 the Choreography Task symbol?
salaboy21 Aug 26, 2011 9:59 AM (in response to raquetti)do you need only a modeler? or a modeler and execution platform for choreography tasks?
Cheers
PS: can you mark this question as answered?
-
4. Re: Has JBPM 5 the Choreography Task symbol?
tsurdilovic Aug 26, 2011 10:15 AM (in response to raquetti)I don't know if any existing tools that include it. Choreography afaik represents interactions between two participants (message exchange) so you could possibly model the same using message (throwing+catching message event nodes) where you send one message from task/participant A to antoehr task/participant B in the same exact process.
-
5. Re: Has JBPM 5 the Choreography Task symbol?
raquetti Aug 26, 2011 10:30 AM (in response to salaboy21)Mauricio: Only the modeler.
Tihomir: Yes, Graphitti+Eclipse BPMN2 include it.. I dont know if there are other..
Thanks all
ps: How can I mark as answer? Sorry.. All here are in German, I cant understand many things..
-
6. Re: Has JBPM 5 the Choreography Task symbol?
raquetti Aug 26, 2011 10:32 AM (in response to raquetti)Ok.. I found as mark