1. Re: jbpm5 process, how to rollback?
salaboy21 Apr 17, 2012 4:11 AM (in response to gigazhang)probably yes.. but in a different way, the node semantics has changed from jbpm4 to jbpm5 so you need to review what are you trying to achieve in order to say that you can implement it or not. Most of the time the business requirement can be implemented in some way or another no matter what are you trying to achieve..
Cheers
-
2. Re: jbpm5 process, how to rollback?
gigazhang May 7, 2012 4:21 AM (in response to salaboy21)I want allow the excutor rollback the flow to the previous step,but if i use the gateway, the view will like weeds...
-
3. Re: jbpm5 process, how to rollback?
gigazhang May 10, 2012 9:15 PM (in response to gigazhang)Scene: my flow have 5 task node, when it flow to 4,the owner found that the second owner have made a mistake.So, the flow must be rollback to the second node.and maybe the first owner made a mistake,or third
Now,how do i do to rollback the flow in application?
thks
-
4. Re: jbpm5 process, how to rollback?
marianbuenosayres Sep 7, 2013 10:17 AM (in response to gigazhang)I know this may come a bit late, but thought it was worth mentioning. I've just developed a module to allow for persistent process rollbacks to a previous safe state. It would allow for you to go back to step 2 when you already made extra steps, without having to specify them in the process definition. The post about it can be found here: http://www.plugtree.com/rollbackable-processes-public-training-london-2013/
Cheers