Hi community,
I have to implement a process with a significant number of nodes but before dealing with the all the process I am testing some parts of the process
So here is the sample (cf added screenshot for something more visual !) :
Start Node => User Task Node => None End Node
On the User Task Node I put a Timer Boundary Interrupting (CancelActivity = true) with 5s of duration followed by a Script Task and then a None End Node.
jBPM version used : 6.0.0.Final
1- Test under eclipse (eclipse BPMN 2 Modeler + a JUnit) :
a- When I run the test wihout dealing with human task, the sysout in Script Task is executed but when I ask for process instance state, response is 1 (ACTIVE) while it should be 2 (COMPLETED) because of the cancel activity state (checked) on Boundary Timer ?
2- Test under jBPM console with Web Designer
b- Whether I set cancel activity to true or false there is no visual difference on process view canvas, I think this not normal !
c- When I Build & Deploy and then run, there is an UserTask displayed in Personal Task even if after timer has been raised but because of cancel activity = true UserTask should be canceled...
d- Created process instances are in ACTIVE while it should be COMPLETED.
Anyone experience this kind of problem?
KR